Executive Summary
This week, payment of the processing fee (₱1,000, billed to the owner) was completed on October 29, 2024, and forwarded for review by John Marlon Alag. The delivery of furniture has been rescheduled to November 25. Pending approval of the work permit, the construction remains tentatively scheduled for completion in the first week of December.
Progress This Week
Response received from admin regarding payment for processing fee
Paid ₱1,000 for processing fee (to be billed to owner) on October 29, 2024
Request forwarded for review by John Marlon Alag on October 29
Rescheduled delivery of furniture to November 25
Upcoming Work for Next Week
Waiting for approval of work permit
Upon approval, scheduling of hauling of old furniture, bathroom works, and carpentry works on day one of start of construction
Schedule Updates
Tentative date of start: November 11, 2024
Tentative date of completion: December 6, 2024
Progress Update:
Response received from the administration regarding the installation of the smart lock for the main door and the air conditioning unit.
Completion of architectural and engineering drawings for the permit.
Scheduled delivery of items with long lead times.
Order placed and delivery scheduled for appliances.
Work in Progress:
Submission of drawings for permit approval is currently underway.
Downpayment received October 8, 2024
Payment received through bank transfer via BPI
Accomplishment
Ordering of furniture with long lead time
Work In Progress
Architectural and electrical plans for permit acquisition.
Awaiting confirmation regarding smart lock and air-conditioning unit installation.
Initial Bill of Materials Presentation
Discussion of scope of work, construction and furnishing details
Presentation of updated renders
Panoramas available under Documents Page
Initial 3D Model Presentation
Presentation of Initial Design Perspectives
Work In Progress
Initial Bill of Materials
Rescheduled
Presentation of Initial Design Perspectives to September 12, 2024 due to closure of office last Monday and Tuesday due to the storm Enteng.
Work In Progress
Initial layout of 3D perspectives
Date: August 29, 2024
Date: August 10, 2024