This week, significant progress was made with the replacement of light switches, installation of lighting fixtures, a smart mirror, bathroom fixtures, and a bathroom lavatory cabinet. Hauling of old furniture and debris was also completed, along with the installation of power supply for the split-type air conditioning unit. However, challenges included adjustments to the water supply line and the identification of old electrical outlets requiring replacement. Due to supplier backlogs on furniture deliveries, the project’s target completion date has been moved to December 20.
Progress This Week
Installation of all lighting fixtures, light switches and new convenience outlets.
Installation of power supply line for split type air conditioning unit
Installation of smart lock
Installation of new bathroom fixtures
Installation of smart mirror
Delivery of Queen sized and single sized mattresses
Delivery of double deck bedframe
Current Issues / Risks
Water supply line is not typical, requiring adjustments to pipes by closing some valves.
Some electrical wires and outlets are old and due for replacement.
Upcoming Work for Next Week
Scheduled final coat and finishing on Monday
Installation of air conditioning units on Monday
Installation of flooring on Wednesday
Delivery of a few furniture pieces on Friday upon payment receipt
Schedule Updates
Target finish date: December 20 (due to supplier backlog on sofa and bed frame orders).
See what part of the project we are currently at.
Day 1
Initial Meeting & Consultation
Ocular Inspection
HOA /Building Requirements
Day 2 - 21
Mood Board Presentation
Initial Design Perspectives & Bill of Materials
Construction Drawings
Day 22 - 50
Work Permit and Gate Pass Acquisition
Construction Works
Furniture, Fixtures, & Accessories Placement
Day 50 - 52
Post Construction Cleaning
Styling and Staging
Final Inspection & Key Turnover
Who, what, and where?
Project Owner
Joseph Manaloto
Project Size
53 square meters
2 Bedroom & 1 Bath
6 Persons
Project Location
Unit 2211 Heliconia Building
Tivoli Garden Residences, Coronado Street
Mandaluyong City, MetroManila Philippines